
The extend of the excavation is
shown in red in the above figure. All of the Phase I spaces have
been excavated except for the lower part of the Cube Hall. This
last volume comprises 8% of the total Phase I excavation and will be
removed in a single blast sequence shortly. Shotcreting (the
spray on concrete linear) is about 75% complete with the lab entrance
done, most of the ladder labs and most of the approach to the Cube
Hall. About half of the Cube Hall has been shotcreted. The
concrete floors have started to be poured with the lab entrance
completed and about 2/3 of the ladder labs. Installation of the
steel work, interior walls, electrical, ventilation etc is expected to
start in late spring or early summer.