SNOLAB
Updates
Excavation of the new SNOLAB
experimental spaces is almost complete with only the wall preparation of the Cryopit remaining.
Outfitting is progressing well and all construction work is expected to
be completed by the end of 2008. The experimental program at
SNOLAB
has a new addition, the DEAP-1 experiment which moved underground at
the end of last year.
Excavation Status
On 29 Dec 2007, the last large blast for the
excavation program was complete when a 38 ft bench was taken in
the Cryopit. A few weeks later, the
breakthrough from the Phase II Cryopit area to the Phase I excavations
was done, completing the major excavation of the laboratory.
To date, approximately 93,000 T of rock has been excavated with
approximately 5,000T remaining. The remaining excavation work
consists of
removing the rock from the Cryopit, installing the ground support (rock
bolts, cable bolts and screen) and applying the Shotcrete (spray on
concrete) liner.
 |
White shows the original
excavations. Orange shows the new excavations. The bottom
2/3 of the Cryopit has been blasted but the rock not yet removed.
|
Once the ground support and shotcrete walls are in place a
second pass of shotcrete which is hand troweled to a smooth finish is
applied. Then the concrete floors for the new excavations will be
poured and the outfitting and services installed.

|
Looking down into the
Cryopit from the main level of the laboratory. The first pass
shotcrete liner can be seen completed part way down the wall. The
scoop tram is sitting on the "muck pile" of broken rock which is
removed from the base of the hall through an access drift. As the
muck is drawn down, the ground support and screening and shotcrete are
applied to the walls of the pit.
|

|
Looking through the
break through from the Cryopit Utility Drift to the Cube Hall Utility
Drift. The block wall visible
in the Cube Hall Utility Drift was constructed to protect the Cube Hall
areas from the concussion of the break through blast.
|
Outfitting
Status
Outfitting of the new lab entrance passed a milestone in
December 2007 when three of the new air handling units (AHUs) were
turned on bringing filtered cooled air into the construction
area. In addition to making it easier to work in an environment
where the normal rock temperature is 42C, the filtration reduces the
dust as part of the process of going from a dirty construction site to
a clean room laboratory. The personnel area (lunch room,
shower and change rooms) is now approximately 80% complete with the
majority of the plumbing, ventilation ducting and electrical wiring in
place. The remaining work in the laboratory entrance is expected
to take until late spring 2008.

|
The "Carwash" where
material will be cleaned prior to being brought from the dirty mine
environment into the cleanroom laboratory.
|

|
One of the new air
handling units (AHUs) which will provide HEPA filtered air to the
laboratory.
|

|
The "Junction" which
connects the new laboratory excavations to the existing SNO
facility. This view is looking north towards the Ladder Labs and
Cube Hall. Two air handling units are located on the mezzanine.
|

|
The new lunch room for
SNOLAB will have approximately twice the capacity of the original SNO
facility and is situated at the top of the original ramp used to
excavate the SNO cavern.
|

|
The Ladder Labs looking
north towards the Cube Hall. The walls are painted and some of
the service support structures are now in place
|

|
This area of the Ladder
Labs is intended to house a "medium" scale experiment (of order 5m
size). But during construction, it is being used as a factory to
fabricate ventilation ducting. Roles of metal banding are brought
underground and rolled into spiral ducting. This is much more
efficient than bringing ducts down prefabricated.
|